Lynchburg District Weekly Traffic Alert September 21-27, 2026
LYNCHBURG — Highway work requiring road/lane/structure closures is planned; however, work may be delayed/canceled due to weather or other issues. Items in italics contain new/updated information. For up-to-date information, call 511 or visit https://511.vdot.virginia.gov
District-wide activities:
Crews will perform various activities throughout the district to include, but are not limited to bridge & guardrail maintenance, brush/tree/limb cutting, pothole/surface/shoulder work, surface treatment/paving operations, work orders, mowing, boom axing, drainage repairs/ work and roadside cleanup.
Work at specific locations:
Amherst County:
Please note district-wide activities above.
Appomattox County:
Route 460 Appomattox Bypass (Richmond Highway) - Road reconstruction. Westbound Route 460 has been reduced to one lane and speed limit reduced to 45 mph through the work zone. Expect delays. An Automated Photo Enforcement system is in place. Maintain proper speed throughout the work zone. Expected completion December 2026.
Buckingham County:
Please note district-wide activities above.
Campbell County:
Route 29 (Wards Road) at Route 699 (Gladys Rd.) - Intersection improvement project. The left lanes of Rt. 29 will be closed in both the northbound and southbound directions in the vicinity of the Rt. 699 (Gladys Road) intersection. The median crossover at the intersection of Rt. 699 and Rt. 29 will also be closed. Traffic coming from Rt. 699 wanting to head south on Rt. 29 will need to make a right turn and then make a U-Turn at the newly constructed bulb-out. Rt. 29 southbound traffic wanting to turn left onto Rt. 699 will need to pass the intersection and make a U-Turn at the next available median crossover or at the Rt. 29 Business exit. Expected completion September 2026.
Please note district-wide activities above.
Charlotte County:
Route 642 (Mossing Ford Road) over Roanoke Creek - Bridge replacement. The bridge over Roanoke Creek is closed with detour in place to direct traffic. Expected reopening December 2026.
Please note district-wide activities above.
Cumberland County:
Please note district-wide activities above.
Halifax County:
Intersection of Route 360 (North Main Street) and Route 501 (L P Baily Highway) - Intersection Improvement Project (Roundabout). Change in traffic pattern expected the week of September 21st, weather permitting, with lane shifts along Route 360 (North Main Street) and installation of all-way stop condition for Route 360 Eastbound and Westbound. Signage will be in place to notify motorists of the changes. Work will be taking place along the shoulders with intermittent lane closures and flagging operations as needed. Expect delays. Expected completion November 2027.
Route 667 (Leda Road) at Bye Creek (36.843876, -79.083870) - Bridge replacement. Leda Road is closed to thru traffic from Route 57 (Halifax Road) to the intersection of Route 753 (Beulah Road). Expected completion October 2026.
Route 501: Huell Matthews Highway from Route 744 (East Hyco Road) to Route 96 (Virgilina Rd.) - Safety improvements. Shoulder widening, rumble strips, and guardrail replacement project. Lane closures expected. Expected completion December 2026.
Please note district-wide activities above.
Lynchburg:
Candlers Mountain Road / Business 29 Interchange - Interchange Improvement and bridge replacement project. Work will be taking place along the ramps, loops, Candlers Mountain Road, and Business 29 in the vicinity of this interchange. Short term lane closures or detours needed for this work will take place at night, between the hours of 8:00 pm and 5:30 am. Lane widths will be reduced to 10' feet on Business 29. Please pay attention to message boards and signs when travelling through this area. The first ramp closures and detours for placement of concrete barriers are expected to occur the week of September 28th. Expected completion August 2029.
Intersection of Wards Ferry Road and CVCC Campus Drive - Intersection Improvement Project (Roundabout). Work will be taking place along the shoulders of Wards Ferry and CVCC Campus Drive in the vicinity of this intersection. Expect temporary flagging operations on Wards Ferry Road and CVCC Campus Drive. Harvard Street is closed at the Wards Ferry intersection, with traffic following a signed detour route along College Park Drive to get to/from Wards Ferry Road. Expected completion November 2027.
Please note district-wide activities above.
Nelson County:
Route 29 (Thomas Nelson Hwy.) and Route 653 (Oak Ridge Road) - Intersection improvement and turn lane project. The right, northbound lane of Route 29 is closed from 0.6 miles south of Route 653 to 0.2 miles north of Rt. 653. The speed limit along Route 29 is reduced to 50 mph while the lane closure is in place. Expect temporary flagging operations on Oak Ridge Road as work is performed on the shoulders and ditches. The expected completion date is October 9, 2026.
Route 29 (Thomas Nelson Highway) from the Amherst County Line to Route 718 (Mountain Cove Rd.) - Safety improvements. Shoulder widening, rumble strips, and guardrail replacement project. Lane closures expected. Expected completion July 2027.
Please note district-wide activities above.
Pittsylvania County:
Route 311 (Harville-Saunders Parkway) - Road widening project. Expect temporary lane closures utilizing flagging operations. Expected completion November 2027.
Please note district-wide activities above.
Prince Edward County:
Please note district-wide activities above.
Legal Disclaimer:
EIN Presswire provides this news content "as is" without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the author above.